Greeley
Staff expect Greeley’s $50 million wastewater upgrades to finish in November 2027
The plant has continued operating during construction. The work adds backup power, new pumps that bring wastewater in and side-stream treatment processes addressing phosphorus and nitrogen.
Greeley’s $50 million wastewater plant upgrades are almost 60% complete and expected to finish in November 2027, a staff member told the Water and Sewer Board on Oct. 21.
Staff said findings of the 2018 master plan drove the upgrades, which generally follow its phasing. The work covers the front end of the plant’s primary processes and includes a generator, a blower and air header, and side stream treatment improvements. The plant has remained in operation during construction.
MagPrex, a new side stream treatment process, is intended to reduce phosphorus recirculated from the back of the treatment process to the front. The staff member said it “was based on projected new phosphorus levels” and could help the city reduce phosphorus over the long term. The work could also help with state voluntary incentive program credits, the staff member said.
Another side stream treatment process, Anita Mox, is being added to the plant. The work involves rehabilitating the centrate building and a tank. The process helps the plant meet regulatory requirements for nitrogen in its effluent, the staff member said.
A medium-voltage generator was planned for a previous major construction project but was delayed because of cost constraints, staff said. The wastewater facility is required to have backup power, staff said. The older generator was taken out of service with the new one, and masonry work in the former generator space was completed over the summer.
Two new pumps that bring wastewater into the plant have been installed. A third is coming. Staff said the pumps were sized according to population growth projections in the 2018 master plan.