Greeley
Greeley working on 175 planned lead and copper replacements
Phase 4 replacements are expected to finish by the end of the year. Final potholing is also expected to wrap up then, with any replacements identified in that phase planned for 2027; the loan-financed project totals $14 million.
Greeley has 175 planned replacements underway in its lead and copper project, staff told the Water and Sewer Board on Oct. 21. Phase 4 replacements were expected to be finished by the end of December.
Staff expected to finish Phase 5 potholing, the project’s final potholing phase, by the end of the year. Any replacements from that phase will be done in 2027. The loan-financed lead and copper project totals $14 million.
8th Avenue reopened Oct. 20, and four crews were working simultaneously on downtown revitalization, a staff member said. The work between 8th and 12th Streets includes stormwater, water, sewer and non-potable improvements. Staff expected it to be complete in October 2028. Project status and parking detours are posted on Speak Up Greeley weekly, sometimes more often as conditions change, the staff member said.
Greeley coordinated its 1st Street water-line replacement with Keep Greeley Moving road improvements to avoid tearing up the road more than once. Construction was expected to start early in 2027 and finish in June 2027, before the Stampede, staff said. The water department’s portion costs $830,000.
The Boomerang North upgrades cost $3.2 million. The Culture, Parks, and Recreation Golf Enterprise Fund pays for the pump station, a staff member said. Golf courses do not pay Greeley for water, a staff member said, describing the arrangement as “a cost trade-off” involving franchise and right-of-way permit fees the city does not pay.
The Gold Hill 60-inch connection will add the remaining 3 miles of pipeline from Bellevue to Zone 4 Pump Station. Design changes were needed because of the Boyd Line relocation, and staff expected construction to run from 2027 through 2028. A board member put the line’s cost at $24 million and called it a generational project with long-term implications for the community.