The NoCo Herald

Larimer and Weld counties, Colorado

What's being built

Every development proposal on file with Fort Collins, Loveland, Greeley and Weld County: what is proposed, where it stands and when it goes before a hearing.

Hearings aheadNext two weeks4

New & changed2

Weld County56 proposals

Case 1Case 2Case 3Case 4Case 5Case 6Case 7Case 8Case 9Case 10Case 11Case 12Case 13Case 14Case 15Case 16Case 17Case 18Case 19Case 20Case 21Case 22Case 23Case 24Case 25Case 26Case 27Case 28Case 29Case 30Case 31Case 32Case 33Case 34Case 35Case 36Case 37Case 38Case 39Case 40Case 41Case 42Case 43Case 44Case 45Case 46Case 47Case 48Case 49Case 50Case 51Case 52Case 53Case 54Case 55Case 56Map © OpenStreetMap contributors
  1. Trucking, Transporation and Contractor's Shop

    31156 County Road 50, Kersey

    Under review Zoning permit for an agricultural or rural use

    A trucking and transportation operation with a contractor’s shop

    ZPAG26-0022 · Weld County planning cases

  2. Winery and Vineyard

    25616 County Road 392, Greeley

    Under review Zoning permit for an agricultural or rural use

    A winery and vineyard in an agricultural zone

    • Farms and animals

    ZPAG26-0021 · Weld County planning cases

  3. Trucking & Transportation Company

    24250 60 1/2, Greeley

    Under review Zoning permit for an agricultural or rural use

    A trucking and transportation company.

    ZPAG26-0020 · Weld County planning cases

  4. Trucking and Transportation Company

    7606 County Road 10, Fort Lupton

    Under review Zoning permit for an agricultural or rural use

    A trucking and transportation company.

    ZPAG26-0019 · Weld County planning cases

  5. Trucking and Transportation Company

    3506 Cr 19

    Under review Zoning permit for an agricultural or rural use

    A trucking and transportation company.

    ZPAG26-0018 · Weld County planning cases

  6. Amend ZPAG23-0014

    27071 County Road 15, Johnstown

    Under review Zoning permit for an agricultural or rural use

    Adding an 8,000-square-foot building for an insulation contractor's shop.

    • 8,000 sq. ft.

    ZPAG26-0017 · Weld County planning cases

  7. Trucking and Transportation Company

    13565 2 1/2, Brighton

    Under review Zoning permit for an agricultural or rural use

    A trucking and transportation company.

    ZPAG26-0016 · Weld County planning cases

  8. Trucking and Transportation Company

    25895 County Road 42, Kersey

    Under review Zoning permit for an agricultural or rural use

    A trucking and transportation company.

    ZPAG26-0015 · Weld County planning cases

  9. Contractor Shop

    9139 County Road 54, Milliken

    Under review Zoning permit for an agricultural or rural use

    A contractor shop

    ZPAG26-0013 · Weld County planning cases

  10. Agritourism Facility

    7990 Cr 1

    Under review Zoning permit for an agricultural or rural use

    A U-pick lavender experience and farm store

    • Farms and animals

    ZPAG26-0012 · Weld County planning cases

  11. Contractor Shop

    2701 F St, Greeley

    Under review Zoning permit for an agricultural or rural use

    A contractor shop

    ZPAG26-0011 · Weld County planning cases

  12. Trucking and Transportation Company

    19495 County Road 44, La Salle

    Under review Zoning permit for an agricultural or rural use

    A trucking and transportation business

    ZPAG26-0010 · Weld County planning cases

  13. Contractor Shop

    33421 County Road 33, Greeley

    Under review Zoning permit for an agricultural or rural use

    A contractor shop

    ZPAG26-0009 · Weld County planning cases

  14. Landscaping Business

    31496 County Road 29, Greeley

    Under review Zoning permit for an agricultural or rural use

    A landscaping business

    • Shops, restaurants and services

    ZPAG26-0008 · Weld County planning cases

  15. Trucking Company

    10756 County Road 20, Fort Lupton

    Under review Zoning permit for an agricultural or rural use

    A trucking company.

    ZPAG26-0005 · Weld County planning cases

  16. Contractor Shop for Heating & Cooling

    6363 County Road 20, Longmont

    Under review Zoning permit for an agricultural or rural use

    A contractor shop for a heating and cooling business.

    • Shops, restaurants and services

    ZPAG26-0004 · Weld County planning cases

  17. Contractor's Shop

    0

    Under review Zoning permit for an agricultural or rural use

    A contractor's shop.

    • Shops, restaurants and services

    ZPAG26-0001 · Weld County planning cases

  18. Contractor Shop

    4060 Martin St, Brighton

    Under review Zoning permit for an agricultural or rural use

    A contractor shop for marble and granite countertops.

    ZPAG25-0007 · Weld County planning cases

  19. Solar Energy Facility

    38561 County Road 43, Eaton

    Under review Use by special review

    A solar energy facility on 76 acres.

    • Energy
    • 76 acres

    USR26-0030 · Weld County planning cases

  20. Solar Energy Facility

    35208 County Road 15, Windsor

    Under review Use by special review

    A solar energy facility on a 116-acre site.

    • Energy
    • 116 acres

    USR26-0029 · Weld County planning cases

  21. Kennel

    24120 County Road 8, Hudson

    Under review Use by special review

    A kennel for boarding up to 21 dogs and 7 cats on a 6.02-acre site.

    • 6.02 acres

    USR26-0027 · Weld County planning cases

  22. Commercial Junkyard and Salvage Yard

    12433 County Road 41, Fort Lupton

    Under review Use by special review

    A commercial junkyard and salvage yard on a 40-acre site.

    • 40 acres

    USR26-0026 · Weld County planning cases

  23. Natural Gas Compressor Station

    0

    Under review Use by special review

    A natural gas compressor station on a 78.84-acre site.

    • 78.8 acres

    USR26-0025 · Weld County planning cases

  24. Tri-Town Paws Kennel

    1988 Mountain View Dr, Erie

    Under review Use by special review

    A kennel in a subdivision on a 0.93-acre site.

    • 0.93 acres

    USR26-0024 · Weld County planning cases

  25. Water Treatment Plant

    0 120 Cr

    Under review Use by special review

    A water treatment plant on a 36.77-acre site.

    • Schools, churches and public buildings
    • 36.8 acres

    USR26-0023 · Weld County planning cases

  26. Lumberyard/Woodworking

    24960 County Road 61, Kersey

    Under review Use by special review

    A lumberyard and woodworking operation on a 0.55-acre site.

    • 0.55 acres

    USR26-0022 · Weld County planning cases

  27. Sand & Gravel Mine

    13473 County Road 17, Platteville

    Under review Use by special review

    Open sand and gravel mining is proposed on 196.4 acres.

    • Mining, oil and gas
    • 196 acres

    USR26-0021 · Weld County planning cases

  28. Kennel

    18250 County Road 19, Milliken

    Under review Use by special review

    A dog boarding kennel for up to 60 dogs on 9.67 acres

    • 9.67 acres

    USR26-0020 · Weld County planning cases

  29. Data Center

    2000 Howard Smith

    Under review Use by special review

    A data center on a 41-acre site

    • Before the Weld County Board of County Commissioners Oct. 19
    • 41 acres

    USR26-0019 · Weld County planning cases

  30. Kennel

    2396 County Road 12, Erie

    Under review Use by special review

    A kennel for boarding up to 30 dogs on a 5.579-acre site.

    • Before the Weld County Planning Commission Nov. 3
    • 5.58 acres

    USR26-0018 · Weld County planning cases

  31. Kennel

    Under review Use by special review

    A kennel for boarding up to 30 dogs on 35.755 acres.

    • 35.8 acres

    USR26-0017 · Weld County planning cases

  32. Oil and Gas Support and Trucking

    Under review Use by special review

    Oil and gas support services and a trucking operation on 8.75 acres.

    • Industry and storage
    • 8.75 acres

    USR26-0016 · Weld County planning cases

  33. Solar Energy Facility

    Under review Use by special review

    A solar energy facility on 35 acres.

    • Before the Weld County Board of County Commissioners Oct. 21
    • Energy
    • 35 acres

    USR26-0015 · Weld County planning cases

  34. Mining

    Under review Use by special review

    A sand mining plant on 39 acres.

    • Mining, oil and gas
    • 39 acres

    USR26-0014 · Weld County planning cases

  35. Commercia Junkyard

    19570 County Road 28, Fort Lupton

    Under review Use by special review

    A commercial junkyard and oil and gas support and service operation on 39.9 acres.

    • Industry and storage
    • 39.9 acres

    USR26-0013 · Weld County planning cases

  36. Event Facility

    2444 County Road 17, Brighton

    Under review Use by special review

    An event facility and campground on 31.00 acres.

    • 31 acres

    USR26-0012 · Weld County planning cases

  37. Trucking Transportation Company

    Under review Use by special review

    A trucking transportation company.

    • Industry and storage

    USR26-0009 · Weld County planning cases

  38. Solar Energy Facility

    2781 County Road 66, Greeley

    Under review Use by special review

    A solar energy facility on 25 acres.

    • Before the Weld County Board of County Commissioners Oct. 21
    • Energy
    • 25 acres

    USR26-0007 · Weld County planning cases

  39. Events Facility

    Under review Use by special review

    An event facility.

    • Shops, restaurants and services

    USR26-0006 · Weld County planning cases

  40. Event Facility

    15600 County Road 6, Fort Lupton

    Under review Use by special review

    An event facility on 39.5 acres.

    • Shops, restaurants and services
    • 39.5 acres

    USR26-0005 · Weld County planning cases

  41. Oil & Gas Support and Service and Trucking Operation

    24963 County Road 16, Keenesburg

    Under review Use by special review

    An oil and gas support and service operation with trucking on 63 acres.

    • Industry and storage
    • 63 acres

    USR26-0004 · Weld County planning cases

  42. Telecommunication Tower

    9836 48 1/2, Milliken

    Under review Use by special review

    A 150-foot telecommunications antenna tower on 12.5 acres.

    • Roads, utilities and lots
    • 12.5 acres

    USR26-0003 · Weld County planning cases

  43. Mining (topsoil)

    0

    Under review Use by special review

    Open topsoil mining on 131.894 acres.

    • Mining, oil and gas
    • 132 acres

    USR25-0013 · Weld County planning cases

  44. Outdoor Storage

    19 E Cr

    Under review Site plan review

    Outdoor storage for construction equipment.

    SPR26-0010 · Weld County planning cases

  45. Outdoor Storage

    Under review Site plan review

    Outdoor storage for RVs and boats

    SPR26-0009 · Weld County planning cases

  46. Convenience Store and Gas Station

    4821 Yellowstone Dr, Greeley

    Under review Site plan review

    A convenience store and gas station

    • Shops, restaurants and services

    SPR26-0008 · Weld County planning cases

  47. Empire Business Park

    2497 W I 25 Frontage Rd, Erie

    Under review Site plan review

    Industrial and office buildings on a 49.579-acre site

    • Homes with shops or offices
    • 49.6 acres

    SPR26-0007 · Weld County planning cases

  48. Car Dealersehip

    Under review Site plan review

    A car dealership on 9.75 acres

    • Shops, restaurants and services
    • 9.75 acres

    SPR26-0004 · Weld County planning cases

  49. Outdoor and RV Storage in the I-2 Zone District

    1492 County Road 11, Erie

    Under review Site plan review

    Outdoor and RV storage, with cargo containers, on 32.238 acres.

    • Industry and storage
    • 32.2 acres

    SPR26-0003 · Weld County planning cases

  50. Outdoor Storage in C-3 Zone District

    312 County Road 19, Brighton

    Under review Site plan review

    Outdoor storage for RVs, boats and cars on 34.9 acres

    • 34.9 acres

    SPR26-0002 · Weld County planning cases

  51. Gilbert Contracting, Inc.

    12706 County Road 4, Brighton

    Under review Site plan review

    Offices, outdoor storage, truck parking and a warehouse on 2.99 acres.

    • Industry and storage
    • 2.99 acres

    SPR25-0005 · Weld County planning cases

  52. Construction Equipment, Truck Parking and Warehouse

    12628 County Road 4, Brighton

    Under review Site plan review

    Offices, outdoor construction-equipment storage, truck parking and a warehouse on 2.08 acres.

    • Industry and storage
    • 2.08 acres

    SPR25-0004 · Weld County planning cases

  53. Chalk Bluffs Wind and Solar Facilities

    68300 E 25 Frontage Rd, Carr

    Under review State interest facility

    A wind facility generating 380 megawatts and two solar facilities generating 425 megawatts, with substations, battery storage and transmission lines, on 25,200 acres.

    • Energy
    • 25,200 acres

    SIF26-0002 · Weld County planning cases

  54. Agricultural to I-3 (Heavy Industrial)

    Under review Change of zone

    Changing agricultural zoning to heavy industrial

    • Before the Weld County Planning Commission Nov. 3
    • Industry and storage

    COZ26-0003 · Weld County planning cases

  55. Raggsdale Reservoirs Project

    8987 County Road 85, Fort Lupton

    Under review Use by special review

    Expanding a mine for sand, gravel, stone and other materials by approximately 27 acres and adding a conveyor belt on 667.97 acres.

    • Mining, oil and gas
    • 668 acres

    1MJUSR26-20-0030 · Weld County planning cases

  56. Amendment to USR-1435 to expand the Nissen Gravel Mine

    Under review Use by special review

    Expanding a sand and gravel mine and adding processing on 164 acres.

    • Mining, oil and gas
    • 164 acres

    1MJUSR26-05-1435 · Weld County planning cases

From City of Fort Collins development review (read Oct. 18), City of Loveland current development (read Oct. 18), City of Greeley development projects (read Oct. 18) and Weld County planning cases (read Oct. 18). A proposal is a plan filed for review, and it may change or be withdrawn before anything is built.