Under reviewUse by special review · USR26-00192000 Howard Smith
- Acres
- 41
Coming up
Where it stands
- Sept. 1Heard by the Weld County Planning Commission
- Sept. 23Heard by the Weld County Board of County Commissioners
- Oct. 2Under review when the Herald began following itUnder Review
- Oct. 19Before the Weld County Board of County Commissioners
What it says
Use by Special Review Permit for a Data Center in the I-1 Light Industrial Zone District (amendment to Site Plan Review 3AMSPR19-99-293)
The site
- Type of use
- All Other
What the agencies said16
| Agency | Response | Date |
|---|---|---|
| Building Inspection | No Response | |
| Emergency Management Office | No Response | |
| Flood Plain | No Concerns | June 12 |
| Health Department | No Response | |
| Development Review | Comments with Conditions | |
| Sheriffs Office | No Concerns | May 7 |
| CDOT | No Concerns | July 16 |
| CDPHE | No Response | |
| Greeley | Advisory Comments | May 26 |
| Severance | No Response | |
| Windsor | Advisory Comments | April 27 |
| Windsor/Severance F-17 | No Response | |
| City of Greeley Water | Advisory Comments | May 26 |
| Whitney Ditch Company | Comments with Conditions | Sept. 3 |
| POUDRE VALLEY REA | No Response | |
| GREAT WESTERN RAILWAY | Advisory Comments |