Under reviewUse by special review · USR26-0015
- For
- Energy
- Acres
- 35
Coming up
- Before the Weld County Board of County Commissioners Oct. 21
Where it stands
- Oct. 2Under review when the Herald began following itUnder Review
- Oct. 6Heard by the Weld County Planning Commission
- Oct. 21Before the Weld County Board of County Commissioners
What it says
Use by Special Review Permit for a Solar Energy Facility (SEF), outside of subdivisions and historic townsites in the A (Agricultural) Zone District.
The site
- Type of use
- Solar Energy Facility
What the agencies said12
| Agency | Response | Date |
|---|---|---|
| Development Review | — | |
| OGED | Comments with Conditions | April 28 |
| Sheriffs Office | No Concerns | April 16 |
| Division of Water Resources | Advisory Comments | May 12 |
| Division of Wildlife - North | No Response | |
| CDOT | No Concerns | April 20 |
| Evans | No Concerns | April 15 |
| Milliken | No Response | |
| Gilcrest | No Response | |
| LaSalle F-9 | Advisory Comments | May 14 |
| School District RE-1 | No Response | |
| Central Weld County Water District | No Concerns | May 6 |