Under constructionSite plan review · 2AMSPR25-82-109379 Cr 34
- For
- Energy
- Acres
- 629
Where it stands
- Oct. 2Under construction when the Herald began following itUnder Construction
What it says
An Amendment to Site Plan Review Permit No. 1AMSPR23-82-10 to 245 kV upgrades to the existing St. Vrain Power Plant substation in the I-3 (Industrial) Zone District
What the agencies said9
| Agency | Response | Date |
|---|---|---|
| Development Review | Comments with Conditions | Jan. 21 |
| OGED | No Concerns | Dec. 19, 2025 |
| Division of Wildlife - South | No Response | |
| Firestone | No Response | |
| Johnstown | No Response | |
| Milliken | No Response | |
| Platteville | No Concerns | Dec. 22, 2025 |
| Platteville F-13 | Advisory Comments | Dec. 18, 2025 |
| Central Weld County Water District | No Concerns | Jan. 6 |