The NoCo Herald

Larimer and Weld counties, Colorado

Greeley

Greeley board OKs using $3.4 million in loan funds for 23rd Avenue tank piping

From the Greeley Water and Sewer Board meeting of

The added unrestricted funds will mostly cover materials and pre-construction costs for transmission-line upgrades; the amended loan also covers lead-service-line replacements across the city's service area.

The Greeley Water and Sewer Board approved an amendment to the city's 2024 state drinking water loan that adds $3,359,704.59 in unrestricted funds to the $7 million piping project at 23rd Avenue and Reservoir Road, alongside the lead service line replacement work.

The money will mostly pay for materials and pre-construction costs. The necessary piping work has been contracted to Connell for $7 million. The amended project description covers identifying and replacing lead service lines throughout the city's service area and reconfiguring and upgrading water transmission lines.

The piping is needed because three storage tanks at 23rd Avenue and Reservoir Road, at Centennial Park, were taken out of service in 2022 following a Colorado Department of Public Health and Environment (CDPHE) Sanitary Survey determination. A staff member said engineering staff determined that the loss of storage could be mitigated by additional piping work instead of rebuilding the storage.

Greeley's original application for the loan proposed spending $15 million to rebuild storage at the site. The presentation says the state encouraged Greeley to remove that project so the lead project could receive the maximum $10 million in principal forgiveness from the federal Bipartisan Infrastructure Law.

The lead service line replacement project is significantly under budget. Greeley found fewer lines needing replacement than expected, and the average replacement cost in year two is closer to $10,000, compared with the $20,000 estimate. Staff projected that final lead-replacement costs would come in well under the $17.6 million in restricted funds.

The $10,000,000 in principal forgiveness and $7,551,020.41 in repayable federal funding were restricted to lead-replacement projects in Colorado. The $3,359,704.59 from the state revolving fund's base funding was unrestricted, and a staff member said it can be used for any purpose CDPHE approves.

A staff member said CDPHE agreed that Phase 5 of the lead replacement was within the existing agreement. A staff member said Phase 5 is everything not in Phases 1 through 4. The state is requiring Phase 5 potholing to verify the basement-inspection program and assumptions about missing service-line data, the staff member said.

The staff member said the only way to guarantee the maximum principal forgiveness the city is entitled to is "to ensure that as much of the loan is spent as can be justified." The staff member also said the Colorado Water Resources and Power Development Authority, which administers the loan, might move some of Greeley's restricted lead-replacement funding to other outstanding lead-replacement projects in Colorado.

Greeley has paid $1,105,845 in principal and interest on the loan, and it pays on the entire repayable balance until the project concludes. Its 2027 principal and interest payments due before then are $591,830.

By December 2027, the unused portion of the loan will be repaid and future debt service on the remaining repayable portion recomputed.

City Council will also be asked to approve a resolution amending the loan agreement, a staff member said. The staff member said a typo in the amendment would be referred to the authority for correction.

More from this meeting

  1. Greeley Water and Sewer Board, Nov. 18, 2026

    Greeley board OKs using $3.4 million in loan funds for 23rd Avenue tank piping; Greeley staff propose changing raw-water requirements for apartments, and cutting them for parks; Greeley water board reviews charter powers over rates and budgets.

  2. Item 6Greeley staff propose changing raw-water requirements for apartments, and cutting them for parks

    The proposals would set different requirements by bedroom count, reduce water dedication for city parkland and revise fees and irrigation rules. Staff will bring them back for discussion and approval in coming months.

  3. Item 7Greeley water board reviews charter powers over rates and budgets

    The charter bars City Council from lowering the minimum water and sanitary sewer rates the board sets.

  4. Item 8Greeley moves home lead and copper testing to a reduced schedule, with none planned until 2028

    Starting in 2027, drinking-water reports must be updated every six months. A separate requirement will add lead monitoring at schools and child-care facilities.

  5. Item 9Greeley board authorizes opposing Gray Mountain and Upper Laramie Aquifer water filings

    The board authorized the filings in cases 26 CW 3148, 26 CW 3151 and 26 CW 3160. The board also authorized staff and legal counsel to seek resolution of issues raised by the cases consistent with Water and Sewer Board Resolution Number 3/2015.