Greeley adopts $4.65 million year-end spending bill, with $2.2 million for sewer projects
The bill also funds lift-station design, police equipment and overtime, rental assistance and supportive services for people experiencing homelessness, plus continued design work for a new city maintenance facility.
Greeley City Council adopted a $4,652,701 appropriation for the rest of 2026, with $2.2 million of it going to sewer projects, including design work on the Windsor Basin Interceptor and design of a lift station for the John Law Basin.
The money comes from $3,271,000 in capital fund balance, $725,901 in new revenue and $655,800 in operating fund balance. The new revenue consists of $545,901 in grants, $100,000 in court fines and $80,000 in audit revenue. Staff said the appropriation would require no additional draw on General Fund balance.
A $1,414,000 sewer construction carryover covers 2025 purchase orders that were not included in the spring carryover process. It supports Water & Sewer projects, including Project 13163's Windsor Basin interceptor design and preconstruction services, cost estimating, final-design support and easement coordination, with work continuing through 2027.
The Water & Sewer Department had received eminent-domain authority for the Windsor Basin Interceptor and was working to obtain the necessary easements. The project description says securing the easements now could help avoid future cost increases, and that obtaining them before other public or private utilities may prevent the need for redesign and reduce challenges to the system.
The appropriation also includes $441,000 to design a lift station and force main for the John Law Basin. The system will deliver wastewater to the Poudre Trunk Main for treatment at the city's wastewater treatment and reclamation facility.
Design is starting in 2026 using $284,379 remaining in the budget for evaluating wastewater infrastructure at the Carestream site. The schedule says $625,000 is needed to complete progressive design-build preconstruction and $100,000 for easements. Construction is anticipated to start in 2027, with customers planned for 2028.
Police grants totaling $393,108, awarded after the 2026 spring appropriation, will support speed LIDAR handheld devices, breath-testing equipment, shooting-range improvements and other grant-eligible operational needs. They will also pay for officer overtime for auto-theft enforcement and impaired-driving work.
Two grants address homelessness and housing. A $31,490 HUD Continuum of Care grant will fund the second half of 2026 and support rental assistance and supportive services to help individuals and families experiencing homelessness obtain and maintain permanent housing.
The 2026/2027 Olmstead Grant appropriation is $201,600, made up of $100,800 from fund balance and $100,800 in revenue. It will support housing, tenancy services and case management for people with disabilities who have experienced homelessness or significant housing instability.
Other items include a $20,503 Phillips 66 swimming grant to help provide lessons to Spanish-speaking or ESL swimming-program registrants. The appropriation adds $100,000 to the code-abatement budget for anticipated higher activity, and the city recoups abatement costs through court fines and fees. It also moves $500,000 in eligible Public Art funds from the Downtown Civic Campus project to the associated Public Art project.
The remaining allocations are:
- $536,000 in a water capital replacement carryover, covering 2025 purchase orders left out of the spring process and continued design and programming for the new City Maintenance Facility, with work continuing through 2027
- $555,000 for the Workers Compensation fund, for previous claims anticipated to settle by the end of 2026
- $80,000 in additional one-time audit revenue the city expects in 2026, to cover additional audit costs
Staff expected this to be the final appropriation of 2026. They said the requests align with the 2027 budget.