Greeley
Greeley council denies continuing hearing on Johnson Subdivision sewer assessments
Owners would pay when they connect to the city sewer, with no interest and installments available for up to five years. Additional sewer-line extensions and plant investment fees would still apply.
Greeley City Council on Nov. 17 denied a motion to continue to Dec. 15 the public hearing and second reading of an ordinance that would charge Johnson Subdivision property owners $12,631.57 each for the new city sanitary sewer.
The proposed assessments would be due when a property connects to the city sanitary sewer system, either at the owner's request or when required by the Greeley Municipal Code.
Unpaid assessments would not accrue interest, and the Director of Water and Sewer could authorize installments over a period of up to 5 years. Properties in the district would remain subject to other city sewer requirements, including any additional sewer-line extensions needed for connection and sanitary sewer plant investment fees.
Johnson Subdivision is north of 4th Street and west of 35th Avenue, and the vast majority of its residential lots had been using aging private septic systems.
The project presentation said state rules require connection to sanitary sewer for properties within 400 feet and that individual owners could have faced $30k to $60k to extend sewer mains. It said the local improvement district was established to pay for a sanitary sewer collection system serving the subdivision and included 38 properties with $480,000 in maximum costs.
A council member said some people who moved into the neighborhood later had not been part of the original discussions and did not know they would be assessed, which "causes a little bit of unrest." The member said the assessment would affect the budget and expressed concern about setting a precedent. Another council member said other neighborhoods using septic systems may eventually have to join the city sewer system at their own cost.
A city representative said the project took much longer than expected and made life difficult for residents.
The representative said construction encountered delays after the COVID era because needed parts were unavailable and the project had trouble retaining labor. The project presentation said Water and Sewer staff handled design and construction to control costs. Construction began in 2021, paused in 2022 because of staffing, restarted in 2023 and finished in 2025.
The presentation said project costs exceeded the first ordinance's estimates because soil conditions were worse than anticipated, increasing construction and paving costs. Total expenses came to $580,857.21, including $302,738.48 for construction and $101,313.24 for asphalt paving.
A council member praised the water staff and said the city had completed a $500,000 project that could have cost about $2 million if a contractor had been hired. The presentation said installed service stubs would save customers an average of $20,000 in construction costs when connecting to the system.
The city representative said that if the assessment ordinance were denied, staff would also seek repeal of the ordinance that established the local improvement district.