Weld County adds $92,150 to City Hall block demolition contract
Patrick O'Neill of the Facilities Department told commissioners that the existing foundations were 16 inches to 24 inches thick, which resulted in additional costs. Change Order 5 also covers additional costs for October stormwater management, site security and fencing, he said.
Weld County commissioners approved a $92,149.85 increase to the contract for demolishing West Block North, bringing its total to $1,719,560.34, after the City Hall block's existing foundations were found not to be as anticipated.
Patrick O'Neill of the Facilities Department told commissioners that the existing foundations were 16 inches to 24 inches thick, which resulted in additional costs. Change Order 5 also covers additional costs for October stormwater management, site security and fencing, he said.
Ancon II Constructors, Inc. was awarded the contract for demolition and abatement of the West Block properties, which the board approved on April 15, O'Neill said. The commissioners reviewed Change Order 5 by pass-around on Oct. 5, he said.