Weld commissioners approve partial vacation of Hiner mining and camping permit

From the Weld County Board of County Commissioners meeting of

The partial vacation was required because the applicant received approval from the Division of Reclamation and Mining Safety for a technical revision reducing the mining area by about 58.3 acres on July 6, 2022, a staff member from the Department of Planning Services said.

Weld County commissioners on Nov. 4 approved a partial vacation of R M Hiner Construction Co Inc.'s permit for an RV campground, mining and roustabout use, after the mining area was cut by about 58.3 acres.

The partial vacation was required because the applicant received approval from the Division of Reclamation and Mining Safety for a technical revision reducing the mining area by about 58.3 acres on July 6, 2022, a staff member from the Department of Planning Services said. The department received the company's request to partially vacate the permit on Oct. 7.

The site has been divided to put mining and camping on the east side and the roundabout and oil and gas support and service on the west side, the staff member said. The proposed division puts the smaller part on the west side. The deeds have been recorded, but the division is not yet shown on the property portal, the staff member said.

Commissioner Kevin Ross said the vacation "solves a lot of the issues that have been associated with this, uh, property." He thanked the applicant for finalizing and adjusting it to get in compliance.

The permit, numbered 3MUSR21-95-1075, was recorded April 30, 2025, for an RV campground, mining and roustabout use in the ag zone.

More from this meeting

  1. Weld County Board of County Commissioners, Nov. 4, 2026

    Weld County OKs up to $250 million in financing for new Justice Center, 4-1; Weld commissioners approve $63,277 in carryover for unemployment program; Weld County adds $92,150 to City Hall block demolition contract; 19 consent items adopted.

  2. Item 1 and Item 10Weld County OKs up to $250 million in financing for new Justice Center

    The emergency ordinance establishes a lease-purchase structure, with annual payments estimated at up to about $22 million and a maximum interest rate of 5.85%. It takes effect immediately and lets the chief financial officer finalize terms within those limits.

  3. Item 3, Item 4, Item 5 and Item 6Weld commissioners approve $63,277 in carryover for unemployment program

    The carryover will support services for people receiving benefits in the next program year. The board also approved four workforce contracts covering adult and dislocated workers, youth, Wagner-Peyser and career access programs.

  4. Item 7 and Item 1Weld County adds $92,150 to City Hall block demolition contract

    Patrick O'Neill of the Facilities Department told commissioners that the existing foundations were 16 inches to 24 inches thick, which resulted in additional costs. Change Order 5 also covers additional costs for October stormwater management, site security and fencing, he said.

  5. Item 9, Item 10 and Item 11Weld commissioners approve three agreements to buy land for County Roads 13 and 50 roundabout

    The largest purchase, under Contract ID #11304, is from Massey Farms, LLLP. Public Works is acquiring 2.241 acres of right-of-way and 0.039 acres of temporary construction easement from the landowner, a Public Works staff member told the board.