Estes Park approves $100,000 more for Prospect Mountain water consultant
The amendment pays JVA to guide the town through a resolution with the contractor, beyond its base contract. The leaking tank remains unresolved as discussions continue.
The Estes Park Town Board approved a $100,000 amendment to consultant JVA, Inc.'s Prospect Mountain Water Project contract, which a speaker said would help the town resolve a leaking tank.
“I noticed that the $100,000 was in contingency, and it will further reduce the contingency,” Trustee Chris Eshelman said. Eshelman asked whether contractor delays and issues were primarily responsible and whether a bond or surety company would cover the cost. A speaker said the project remained within its total budget and the amendment would not push it over.
A reasonable solution for the tank leakage has been identified but not implemented, the speaker said. Discussions with the contractor, its legal counsel and technical experts are continuing, and the amendment would pay JVA to guide the town beyond its base contract through a resolution with the contractor, the speaker said. Not all the steps to resolve the broader project issues have been identified, but a path forward has been mapped with the contractor; the next step is to carry it out and assess progress, the speaker said.