Eaton plans to rebuild three roads by end of 2027 with bond of up to $5 million

The Town said the bond authorizes it to borrow up to $5 million against the 1% transportation sales tax voters approved in 2023 for the projects. It will repay the bond at a fixed $380,000 per year for 20 years using the existing tax, the Town said.

Eaton plans to rebuild three roads, including 10th Street from U.S. Highway 85 to Christensen Avenue/County Road 39, by the end of 2027 using a bond of up to $5 million that voters approved Nov. 3, the Town said.

The Town said the bond authorizes it to borrow up to $5 million against the 1% transportation sales tax voters approved in 2023 for the projects. It will repay the bond at a fixed $380,000 per year for 20 years using the existing tax, the Town said. Approval allows the Town to repair its three highest-priority roads years sooner than planned without a new tax, the Town said.

The bond will fund reconstruction of three roads made up of four road segments, the Town said. They include 10th Street from U.S. Highway 85 to Christensen Avenue/County Road 39, Christensen Avenue/County Road 39 north of Collins Street, and Cheyenne Avenue south of Collins Street.

In spring 2027, the Town plans to post three separate requests for bids, collect contractor bids and award construction contracts after Board approval. The anticipated schedule calls for rebuilding the roads from late spring through fall 2027. More than one contractor may do the work.

During winter 2026-27, the Town expects to complete engineering, field investigations and funding arrangements and coordinate with utilities and other agencies.

While repaying the bond, the Town will continue budgeting about $470,000 a year for regular road maintenance and repair. The 10th Street project is partly funded by an Energy/Mineral Impact Assistance Fund (EIAF) grant from the Colorado Department of Local Affairs.

The Town plans to share specific construction dates, project order and traffic impacts as plans and contractor schedules are finalized. Dates may change as engineering, approvals, weather and construction conditions are confirmed. The Town plans to post updated project costs once bids are received and approved.

By the end of 2027, the Town expects to finish remaining work, make final payments and close out the projects.