The NoCo Herald

Larimer and Weld counties, Colorado

Weld County

Roundabout work at WCR 74 and 31 to begin Nov. 30, with temporary closure through Oct. 1, 2027

Weld County says steps will be taken to preserve access to nearby residences and businesses during construction. Detour information is available on the county’s Road Advisory Map.

Work is scheduled to begin Monday, Nov. 30, on a roundabout at Weld County Road (WCR) 74 and WCR 31, with a temporary closure approved by the Weld County commissioners to run through Friday, Oct. 1, 2027.

The Weld County Board of Commissioners approved a temporary closure that will begin when the project starts and remain in place through Friday, Oct. 1, 2027. Detours can be viewed on the Weld County Road Advisory Map.

Weld County Public Works said it has worked throughout project design and planning to make local access to residences and businesses a priority. "Steps will be taken to provide access to nearby residences and businesses throughout the project," said Curtis Hall, the department's director.

The roundabout is intended to improve safety and efficiency by reducing the likelihood of broadside crashes and delays at the intersection, the county said. Approximately 8,100 vehicles pass through the intersection daily.

"Over the past several years, we've seen traffic on Weld County Road 74 increase in general, and it's a trend we expect to continue," said Kevin Ross, Weld County commissioner and coordinator of public works. "Improvements like this one are important to increase safety, particularly as Weld County continues to grow."

The roundabout is to have a concrete driving surface and lanes wide enough for regular vehicles, agricultural equipment and semis to pass through. Planned drainage enhancements are intended to make the intersection more resistant to heavy rain and less likely to be covered in water, as it has been in recent years, the county said.

W.W. Clyde will construct the roundabout, and public works will manage the project. The company finished the roundabout at WCR 74 and WCR 33, which opened in 2024. It also built the roundabout at WCR 6 and WCR 13, which opened in 2025, 26 days ahead of schedule.

The project will be the eighth county-built roundabout since 2020. "We know road projects can be an inconvenience, and we appreciate the public's patience as we work on this roundabout," said Scott James, Weld County commissioner chair. "We believe it will have a positive impact, just like the others we've built."

The Federal Highway Administration says roundabouts reduce fatalities and serious injury crashes nationwide by more than 80%, the county said.