Estes Park board leans toward Riverside Drive for second trail route

From the Estes Park Town Board meeting of

The Moraine Avenue portion will proceed regardless, while grants could fund part of an added alignment. No vote was taken; costs for the first segment would shape what remains for another route.

Estes Park Town Board members leaned toward adding a trail along Riverside Drive to the Moraine Avenue Trail project, a staff member said after hearing their views, though no vote was taken and the river route also had backers.

The town will design and build a trail within the Moraine Avenue right-of-way between Mary's Lake Road and Davis Street regardless of the board's direction on additional routes, staff said.

Staff asked the board whether to pursue the river alignment, the Riverside Drive alignment or neither as an addition. Staff found easements beside the Big Thompson River between Moraine Avenue and Riverside Drive, then obtained approval from NAPMI to revise the grant scope to explore a trail there.

Grant money is what raised the question. The project received $300,000 in state MMOF funds for design with no local match, and NAPMI funding through CDOT for design and construction. A staff member confirmed to Trustee Mark Igel that the availability of grant funding was prompting consideration of the additional alignments.

Staff believed its conservative grant estimate would leave funds to design and build part of one additional alignment. Staff said the NAPMI money could be divided between design and construction, so the town could design Moraine Avenue first, estimate its construction cost and use what remains for some design or construction on one secondary route.

A staff member said what staff were hearing was more desire for the Riverside Drive alignment at that point, and Mayor Gary Hall agreed with that read.

Hall described the project as one loop, saying "this is a loop, not 2 trails," and leaned toward Riverside Drive as a functional multimodal route that would continue the town's loops. Trustee Jamie Mieras also favored Riverside Drive, saying it would serve more town residents and better match the Estes Valley Master Trails Plan.

Mayor Pro Tem Kirby Hazelton said she personally preferred the riverfront experience but favored Riverside Drive as the more practical option. She said it fit the Trails Master Plan and offered potential stormwater-capacity improvements, adding, "I think the stormwater piece is so big."

Staff said Moraine Avenue and Riverside Drive would add pedestrian routes where none currently exist along high-vehicle-volume corridors. It cited safety, fit with the Estes Valley Master Trails Plan and possible stormwater improvements as benefits. Staff said the Moraine Avenue, Riverside Drive and Mary's Lake Road loop is identified in the Valley Master Trails Plan, but the river alignment is not specifically included.

Trustee Frank Lancaster favored the river route for its recreational value and for trails that are "separated from traffic, from the noise, from the pollution." He viewed Moraine Avenue as the strongest point-to-point transportation route and considered Riverside Drive less direct and less attractive for recreation. Lancaster also described a possible larger loop that would connect the Fall River Trail through the park and Sheep Meadows, then return to town through this corridor.

Staff characterized the river alignment as primarily aesthetic and recreational. Staff said it fit the Parks and Open Space Master Plan's emphasis on connections within river corridors.

Some trustees doubted the need for a second trail. Igel said grant availability alone was not a strong reason to pursue a project of that size. If the town pursued a secondary route, he favored Riverside Drive but wanted Moraine Avenue completed and its costs and business and parking access challenges assessed first.

Trustee Bill Brown said, "I can't imagine why we would build 2 myself."

Lancaster called for more community outreach that included nearby residents, trail users, the bike coalition and people who recreate. He said residents next to the route should not be the only voices heard: "that's not the only viewpoint that needs to be heard." Staff said it had heard both positive and negative feedback from community members, particularly people in the neighborhood, about the river alignment.

The existing easement connection ends at the WorldMark property marked 11 on the map, with no current route back to Moraine Avenue or Riverside Drive. Staff estimated that two to three properties might need to be approached for a connection, and said any willing property owner could potentially grant an easement. Staff reported that some owners it had spoken with were uninterested while others had verbally expressed interest in supporting a possible easement.

Staff said either additional alignment would require acquiring easements to make a full connection to existing rights-of-way or trail systems. Staff said the Riverside Drive option would also require easements or right-of-way because some properties have not dedicated right-of-way and some existing rights-of-way are very narrow.

Staff said only one or two areas of the river alignment might fall below the top of the riverbank. Many existing footpaths are on higher, flatter ground, staff said, and some of them are within a special flood hazard area. A trail on the higher ground would add impervious surface but have less significant flood implications than one below the riverbank, which would require different mitigation, staff said.

Staff said a flood on the river route could leave debris requiring cleanup. It said maintenance would depend on what was built and could include vegetation management or trimming branches. Snow plowing would be involved, staff said, and it described plowing as a major maintenance task on trails generally.

Staff based its $4.5 million construction-funding request for the Moraine Avenue Trail on Fall River Trail bid prices from 2023. Staff said 50% of the bid items or unit prices on the most recent Fall River Trail project came in significantly below its estimates. It hoped that trend would leave money for improvements to a secondary alignment if it continued through construction bidding.

Staff said it might be possible to build a segment of one secondary alignment, but the length affordable with construction funds was not yet known.

Staff planned to issue a request for proposals for a design consultant in the first quarter of 2027 and wanted board direction and public input before doing so. Staff expected design to take at least one year. If it began in July 2027, it could run into mid-2028, with construction potentially starting in late 2028 into 2029 or 2029 into 2030, depending on several variables.

Staff said pursuing the river alignment would not require a change to the grant agreement approved in July. Pursuing Riverside Drive would require an administrative amendment to that agreement and a board decision, staff said. The Riverside Drive amendment would return to the board for a vote.

More from this meeting

  1. Estes Park Town Board, Nov. 24, 2026

    Estes Park extends building services contract with SAFEbuilt through 2027; Estes Park approves design work for Big Thompson channel flood project, 5-2; Estes Park trustees tell staff to move ahead with 16 homes per acre in RM zoning district; 4 consent items adopted.

  2. Item 5Estes Park extends building services contract with SAFEbuilt through 2027

    The arrangement leaves the town with 10% of building-service fees, while the contractor receives the rest. Annual fees have been estimated at $400,000 to $500,000.

  3. Item 2Estes Park approves design work for Big Thompson channel flood project

    The contract draws on 1A stormwater funds for engineering and design, but does not commit the town to construction. A cost-benefit analysis would come before any construction project.