- Windsor Town Board, Nov. 23, 2026
Windsor advances downtown parking rules with 85% occupancy target; Windsor adopts housing plan recommending duplexes and bigger multiplexes; Windsor adopts $194.2 million budget for 2027, led by sewer plant work; 5 consent items adopted.
- Item C2Windsor advances downtown parking rules with 85% occupancy target
The ordinance would add a new Article II.V on the Downtown Parking Management Plan to Chapter 8 of the Windsor Municipal Code.
- Item C3 and Item C4Windsor adopts housing plan recommending duplexes and bigger multiplexes
The plan estimates a need for 6,359 to 7,734 new homes by 2033, with 58% for moderate- and lower-income households; its actions are guidance, not requirements for the town.
- Item C5 and Item C6Windsor adopts $194.2 million budget for 2027, led by sewer plant work
The plan also funds road and intersection upgrades, park projects and a shooting range, while setting aside $42,000 for housing assistance. Authorized staffing rises by 6 FTE.
- Item C7 and Item C8Windsor keeps property tax rate at 12.03 mills for 2027 budget
The levy applies to taxable property in Larimer and Weld counties and is expected to fund general operations; no tax was levied for bonds and interest. The Town Clerk must certify the levies to both counties.
- Item C9Windsor adopts water rates; staff put typical household utility bill up about 10% in February
The increase combines higher water, sewer and drainage charges. For a ¾-inch single-family account, the base fee is $30.45, with usage rates reaching $19.96 per 1,000 gallons above 22,500 gallons.
- Item C10Windsor raises monthly residential sewer fee to $54.09 from $48.08
The flat charge applies to single-family homes regardless of water use, beginning with the billing period that starts Feb. 1, 2027. The resolution also sets new base and usage rates for commercial and industrial customers.
- Item C11Windsor raises water tap fee 22.1% to $10,633 for 3/4-inch meters
The fee schedule varies by meter size and applies to land-use approval applications submitted on or after dates set in the resolution; the increase begins Jan. 1, 2027.
- Item C12Windsor raises sewer plant fees, up to $331,864 for largest meters
The revised schedule ties charges to water-meter size and applies to land-use approval applications submitted on or after Jan. 1, 2027. The Town Board may amend the fees at any time.
- Item C13Windsor board takes up higher stormwater fees that would start Feb. 1
The proposal sets a per-square-foot impact fee for new development and monthly charges based on impervious area, including a $3.62 base operations fee, $1 for mosquito control and a separate basin-improvement rate.
- Item C14Windsor approves downtown authority budget with zero net mill levy
The plan appropriates $863,045 for business, projects and programs, including $215,000 for capital improvements. The Town Clerk must certify the levy to county officials by Dec. 15.