Fort Collins moves to join NISP water storage instead of expanding Halligan
The city estimates $200 million in savings from storing its own water in Glade Reservoir with senior rights. Staff plan to present interim-agreement terms in January 2027; a final contract would follow in mid-2027 if both parties accept future terms.
Fort Collins City Council approved a staff recommendation on Nov. 3 to pursue participation in the Northern Integrated Supply Project (NISP), which the city says would replace its plan to expand Halligan Reservoir, with estimated savings of $200 million.
Transitioning to NISP would save Utilities water customers money through smaller rate increases and lower overall costs now and through the life of the project, the city said. Its current rate projections show future increases would not be as high as they would be if the city continued with the Halligan Project.
The city estimates the $200 million in savings is based on its ability to store its own water using its senior water rights in Glade Reservoir.
The city is targeting 5.8% participation in NISP's Glade component, which would provide up to 9,860 acre-feet of storage. Utilities staff determined that storing water using the city's senior water rights in NISP's Glade Reservoir, northwest of Fort Collins, would be a more affordable option for Utilities. The city said that affordability, together with significant permit challenges, led to the recommendation to pivot to NISP.
Fort Collins has worked on federal permitting for the Halligan Water Supply Project since 2006. The U.S. Army Corps of Engineers signaled that the proposed Halligan Reservoir expansion would be unlikely to get approval when other alternatives, including NISP, have fewer environmental impacts, the city said.
The Halligan Project's Clean Water Act Section 401 Water Quality Certification was appealed in July 2026. Fort Collins staff have withdrawn the project's federal permit application with the Corps.
Staff plan to present new information to City Council in January 2027 and outline terms for the next interim agreement. If future Northern Water contractual agreements are accepted by both parties, the city would sign a final contract to officially become a NISP participant in mid-2027.
The city will host two information nights for the public to learn more and ask questions.
Securing storage is a strategy to ensure the city's ability to capture water using its senior water rights to meet community needs in a warmer, higher-volatility future for generations to come, the city said. Its comprehensive water conservation program has helped significantly reduce the amount of storage needed.
Conservation efforts and investments do not provide the scale of resilience that more storage does, the city said. It said it needs both storage and conservation to stretch existing supplies and ensure Utilities can serve the community through drought.
Fort Collins Utilities staff began reevaluating available water storage alternatives in 2025 as part of due diligence before significant capital investment in Halligan Project construction. Staff executed a 2026 interim agreement with Northern Water under City Council authorization and direction.
The city and Northern Water have a long partnership for water delivery through the Colorado-Big Thompson Project and Horsetooth Reservoir, west of Fort Collins.